The MacIsaac Hall, (the gym-building project) is coming along slowly but surely!
Although the indoors still look pretty much the same, there are alot of behind-the-scenes things going on. The sprinkler system is well underway, as well as electrical, insulation, a new cement floor for the basement and the cement stairs come next week. The HVAC system has just been started and sheetrock for the gym proper is the next thing to lineup!
Outside, the landscaping is finally beginning. There are retaining walls going up and brick walkways being prepped, also the masonry block columns for the front will be started next week.